Purchasing — Quotes, POs and Receiving

Buying materials for a job, from asking three suppliers what it costs through to booking in what turned up and billing it. Each step carries its detail into the next, so nothing is typed twice.

Estimate → Quote Request → Purchase Order → Receiving → Bill

Where it lives

1

On the Project, as tabs

Purchasing belongs to a job rather than sitting on its own, so quotes, purchase orders and receiving are tabs on the Project. What you buy stays attached to what you are building.

1. From the estimate to a quote request

1

Pick the lines you want priced

Create Quote Request from Estimate opens the estimate's items so you can tick the ones to send out. The descriptions and quantities you already worked out become the request — you are not retyping a materials list you wrote last week.

This is the step that makes the rest worth using. A quote raised from the estimate stays comparable with it, so "we priced it at X and the supplier says Y" is a question you can actually answer.
2

Or start one from scratch

The round + button raises an empty quote for a vendor. Each carries the vendor and their contact, the quote date, a Required By date and your own reference number.

2. The quote's life

!

The buttons change with the status — that is why one you want is missing

DraftBeing prepared. The only action is Send.
SentIt has gone out. You can now Mark Acknowledged or go straight to Approve.
AcknowledgedThe vendor confirmed they got it. Approve is available.
RespondedThey have come back with prices. Approve is available.
ApprovedYou are going with this one. Convert to PO appears — and only now.
So "where is Convert to PO?" almost always means the quote is not Approved yet. The order of the buttons is the order of the work, and a step cannot be skipped by hunting for a button that is not there.
2

"Mark Acknowledged" is you saying so, not the system detecting it

ClientManager does not watch the vendor's mailbox. That button records staff confirmed the vendor replied — it is a note that a human made, and it is only as true as the person who pressed it.

It is also optional. A quote can go from Sent straight to Approved when the supplier simply phoned the price through.

Asking several vendors — competitive bids

A quote request does not have to go to one vendor. Build the same request for two or three and you have competitive bids on the same work, which is the point of asking at all.

  1. Raise a quote request from the estimate, as above.
  2. Raise another for the same estimate lines, addressed to a different vendor.
  3. Send them. Each vendor sees only their own.
  4. When the prices come back, approve the one you want.
Approving one rejects the others automatically. Any other open quote covering the same estimate lines is marked Rejected in the same moment — so the same work can never be ordered twice from two vendors. It is matched on the estimate lines, not on the vendor or the description, which means it works even when two vendors have described the job differently.

Only a quote that has actually been sent can be approved. A draft cannot, and neither can one already approved or rejected — this is money, so a wrong click is refused rather than quietly accepted.

The rejected ones stay on the project with their prices, which is worth more than it sounds: next time you price similar work, last quarter's losing bids tell you what the market said.

3. The purchase order

1

Converting brings the lines across

Convert to PO turns the approved quote into an order, carrying its items. Add Item adds anything that was not quoted, and clicking an item's description opens it for editing.

Get the quantities right before it is received against. The PO's quantities are what "Ordered" means on the receiving tab, and that is what every outstanding figure is measured from.

4. Receiving what turns up

1

A line per item, and three numbers that do the work

OrderedWhat the PO says.
ReceivedWhat has arrived so far, across every delivery.
RemainingWhat is still outstanding — the number to look at when chasing a supplier.

You then type what came this time into Receive Qty and press Record Receipt.

Partial deliveries are the normal case, not an exception. Record each one as it arrives; the running totals do the arithmetic. Three deliveries against one order are three receipts, and Remaining tells you where you stand after each.
2

Returns go on the same line

Return Qty and a Return Reason sit beside the receive box, so sending back the broken half of a delivery is part of booking it in rather than a separate exercise. The reason is worth filling in — it is the only record of why when the credit note is queried.

5. Billing it

1

Create Bill from Receiving

Once something has been received there is a Create Bill from Receiving button. The bill is built from what actually arrived rather than from what was ordered.

That distinction is the point of the whole chain. Billing from the order pays for goods that may never have turned up; billing from receiving pays for what is on site. If the button is not offered, nothing has been received yet that is not already billed.

What to watch

!

Three honest limitations

Nothing is emailed to the vendor for you. "Send" moves the quote's status; getting it to the supplier is still your email, phone or portal.

Nothing chases anybody. Required By is recorded, not watched — no reminder fires when a date passes. Important Dates is what watches dates.

Quotes are not compared for you. Three quotes from three suppliers are three records; deciding which is best is a human reading them side by side.