The Project Schedule

Three views of the same dates — a calendar, a list and a Gantt chart with dependencies and a critical path — plus the two checkboxes that decide whether the client, the trade partner, or neither gets to see a given date.

Where it lives

→

Open a Project → the Schedule tab

Everything below is on that one tab. The three buttons at the top left — Calendar, List, Gantt — are three ways of looking at the same rows, not three separate schedules. An edit in one shows up in the others.

Which view, and when

1

They answer different questions

ViewAnswersGood at
Calendar“What is happening on the 14th?”Day, week, month and timeline layouts. The only view that handles repeating items.
List“Show me everything, sorted and filtered.”Filtering, printing, Excel export, and the full edit dialog.
Gantt“What is waiting on what, and what slips if this slips?”Phases, dependencies, progress, and the critical path.
Adding items is the same everywhere: the round + button at the top. The Gantt is for arranging what already exists, not for typing it in.

The Gantt view

2

Drag the bars

Do thisAnd it
Drag a bar sidewaysMoves the task, keeping its length.
Drag either end of a barChanges when it starts or finishes.
Drag the small handle at the end of one bar onto anotherMakes the second wait for the first. The arrow between them is the dependency.
Drag the progress handle inside a barSets how far along it is.
Edit a cell in the left-hand gridThe same thing, typed instead of dragged.

Every one of those saves straight away — there is no Save button on the chart and nothing to remember.

The critical path is the point of the dependencies Tasks drawn in red are the ones where losing a day loses the whole project a day. Everything else has slack. That distinction only exists once tasks know what they are waiting for, which is why it is worth linking them up rather than just typing dates.
3

Phases

Any task can sit under another one, which makes the outer task a phase — a heading with a summary bar spanning everything inside it. Set it on the schedule item itself: open it from the List view and use Part of.

There is no separate “create a phase” step. A task becomes a phase the moment something is put under it.
Deleting a phase keeps its tasks They move up to sit beside it rather than disappearing with it. Deleting a heading should not quietly delete a fortnight of work — so the tasks reappear one level up, where you cannot miss them. Delete them individually if that is what you meant.
4

Milestones

A schedule item with no end date is a moment rather than a span — an inspection, a delivery, a handover — and the Gantt draws it as a diamond instead of a bar. Leave End Date empty to get one.

It works the other way too: drag a bar until it starts and ends on the same day and it becomes a milestone, and the List view goes back to showing it with no end date.
5

What the chart will not change

Dragging a bar can only ever change dates, progress, dependencies and which phase a task is in. It cannot touch the owner, the status, or either visibility checkbox — those are only editable in the dialog, where you can see them.

Deleting is not available in the Gantt, on purpose. Delete from the List view instead, where the row you are deleting is the row you are looking at.

Who sees which dates

6

Two checkboxes on every schedule item

Open any item from the List view. Near the bottom: Client Visible and Vendor Visible. They are independent, and both default to off — a new item is internal until you say otherwise.

TickedWho sees itWhere
NeitherStaff onlyNowhere outside CM
Client VisibleThe client on that projectPortal → Schedule
Vendor VisibleTrade partners on that projectPortal → Schedule
BothEveryone attached to the projectPortal → Schedule
One schedule, three audiences The homeowner sees milestones and inspections. The electrician sees the days their crew is on site and the delivery they have to be there for. Neither sees the other's rows, and neither needs a licence, an invitation to a second app, or any training — it is the portal they already use for quotes and invoices.

A contact who is both a client and a vendor on the same project — which happens — sees the union of the two, not one or the other.

What a trade partner actually sees

7

Portal → the project → Schedule

Between Purchase Orders and Bills & Payments, which is the order the work happens in: quote, order, turn up, invoice. Read-only — description, start, end, status and owner — with a line reminding them dates can change.

If nothing has been shared they are told exactly that, rather than being shown an empty table that reads as “there is no plan”. They should ask, not assume.

Limits worth knowing