Three views of the same dates — a calendar, a list and a Gantt chart with dependencies and a critical path — plus the two checkboxes that decide whether the client, the trade partner, or neither gets to see a given date.
Everything below is on that one tab. The three buttons at the top left — Calendar, List, Gantt — are three ways of looking at the same rows, not three separate schedules. An edit in one shows up in the others.
| View | Answers | Good at |
|---|---|---|
| Calendar | “What is happening on the 14th?” | Day, week, month and timeline layouts. The only view that handles repeating items. |
| List | “Show me everything, sorted and filtered.” | Filtering, printing, Excel export, and the full edit dialog. |
| Gantt | “What is waiting on what, and what slips if this slips?” | Phases, dependencies, progress, and the critical path. |
| Do this | And it |
|---|---|
| Drag a bar sideways | Moves the task, keeping its length. |
| Drag either end of a bar | Changes when it starts or finishes. |
| Drag the small handle at the end of one bar onto another | Makes the second wait for the first. The arrow between them is the dependency. |
| Drag the progress handle inside a bar | Sets how far along it is. |
| Edit a cell in the left-hand grid | The same thing, typed instead of dragged. |
Every one of those saves straight away — there is no Save button on the chart and nothing to remember.
Any task can sit under another one, which makes the outer task a phase — a heading with a summary bar spanning everything inside it. Set it on the schedule item itself: open it from the List view and use Part of.
A schedule item with no end date is a moment rather than a span — an inspection, a delivery, a handover — and the Gantt draws it as a diamond instead of a bar. Leave End Date empty to get one.
Dragging a bar can only ever change dates, progress, dependencies and which phase a task is in. It cannot touch the owner, the status, or either visibility checkbox — those are only editable in the dialog, where you can see them.
Open any item from the List view. Near the bottom: Client Visible and Vendor Visible. They are independent, and both default to off — a new item is internal until you say otherwise.
| Ticked | Who sees it | Where |
|---|---|---|
| Neither | Staff only | Nowhere outside CM |
| Client Visible | The client on that project | Portal → Schedule |
| Vendor Visible | Trade partners on that project | Portal → Schedule |
| Both | Everyone attached to the project | Portal → Schedule |
A contact who is both a client and a vendor on the same project — which happens — sees the union of the two, not one or the other.
Between Purchase Orders and Bills & Payments, which is the order the work happens in: quote, order, turn up, invoice. Read-only — description, start, end, status and owner — with a line reminding them dates can change.
Ref_ScheduleStatus ships with no rows, so the Status dropdown offers nothing until statuses are added under Reference Admin.