The Project Budget tab
What a project was supposed to cost, what it has actually cost, and what the client has been billed — on one screen, with nothing to type in.
Where it comes from
Where: open a project → the Financials group → the Budget tab.
There is no budget to fill in. The budget is the accepted estimate. When you accept an estimate it becomes the contract, and this tab measures everything against it. If a project has more than one accepted estimate — a change order signed later, for instance — they are added together.
The three panels
| Panel | What it tells you |
|---|---|
| Budget | Contract value (what the client agreed to pay), budgeted cost (what the estimate said the work would cost, before markup), and the margin between them. |
| Actual cost | Supplier and subcontractor bills, expenses booked to the project, and any commission or referral-incentive payouts recorded on the Commissions tab. Underneath, how that compares with the budgeted cost — green is under, red is over. |
| Billed to the client | Invoices raised, less any credit memos, and what share of the contract that is. |
The two margins are not the same number
Budgeted margin is what the estimate promised: contract value less estimated cost. It never moves.
Projected margin is what the job looks like now: contract value less what it has actually cost. Watching the gap between the two is the point of the screen — it widens the moment real costs run past the estimate.
Two things worth knowing
Expenses count as soon as they are entered, whatever their approval state. An expense that has been submitted is money already spent on the job; leaving it out until someone approves it would make a project look under budget at exactly the moment costs are piling up.
A commission counts once it is recorded, not once it is paid. Same reasoning as expenses — a commission entered on the Commissions tab is money the project owes, whether or not a Payment Date has been filled in yet. The Commissions line only appears on this screen once at least one is on file; a project with none shows the same three-row Actual cost list it always has.
Only accepted estimates count. Draft estimates, and copies made while trying out options, are ignored however many of them sit on the Estimates tab. If the contract value looks wrong, that tab is the place to check which estimate carries an accepted date.
Revising an accepted estimate
Work often gets re-priced after it has been agreed: you copy the accepted estimate, change it, and the client accepts the new one. Both now carry an accepted date, but the job is still one job — so only the most recently accepted estimate in that chain counts, and a note under the budget tells you one was superseded.
That also covers the client changing their mind. If they go back to the earlier version, accept it again: the later acceptance date makes it the live one and the budget follows. There is no "obsolete" box to tick and nothing to undo.