Per-Thousand Units on an Estimate

Three units of measure whose cost ClientManager works out from the rest of the estimate instead of you typing a quantity — for the charges that scale with the size of the job: supervision, coordination, overhead.

The problem they solve. Some lines are not "so many of something". They are "a bit of the job". Supervision on a $40,000 kitchen is not the same number as supervision on a $400,000 addition, and typing a quantity means recalculating it by hand every time the estimate changes — which means it is wrong by the time the estimate goes out.

1. The three units

CodeNameCharges per $1,000 of…
$CPer Category Thousandthe category this line sits in, within its phase
$PPer Phase Thousandthe phase this line sits in
$MPer Estimate Thousandthe whole estimate

They came across from ImproveBuild with the rest of the unit list and have been selectable in ClientManager all along — but until recently nothing calculated them. A line marked $M was extended as quantity × unit cost like any other, so a "plus per $1,000 of contract amount" line with a typed quantity of 1 charged a flat amount instead of scaling. If you have older estimates using these codes, their totals were understated. They are correct from now on.

2. Using one on a line

  1. Add the line as normal — description, category, phase.
  2. Set UOM to $C, $P or $M.
  3. Enter the unit cost: what you charge per $1,000. A supervision line at $10 per thousand means $10 for every $1,000 of the base.
  4. Leave the quantity alone. It is worked out for you, and anything typed there is ignored.

The quantity shown is the base divided by 1,000. On a $200,000 base that is 200, so a $10 unit cost extends to $2,000. Change anything in the estimate and it follows.

A line whose base cannot be worked out extends to zero, not to its typed quantity. That happens when there are no ordinary lines for it to charge against. Zero is deliberate: falling back to the typed quantity would produce a plausible small number — a $10 that should be $2,000 — and a plausible wrong number is worse than an obvious one, because nobody questions it.

3. What each one charges against

Take an estimate with two phases:

LinePhaseCategoryCost
Framing laborShellLabor$30,000
LumberShellMaterial$20,000
CabinetsFinishMaterial$50,000
A line with…sitting in…charges against
$CShell / Material$20,000 — that category, in that phase
$PShell$50,000 — the whole Shell phase
$Manywhere$100,000 — the whole estimate

$C is keyed by phase and category. The same trade can appear under two phases, and a $C line charges against its own phase's share of it — not that category's total across the whole job.

4. Why they never charge against each other

The base for every per-thousand line is the total of the ordinary lines only. A $M line never charges against another $M line, or against a $C or $P line.

Without that rule the arithmetic has no answer. A $M line's cost depends on the estimate total, which contains every line — including other $M lines. Two of them inflate each other, and the result depends on which you calculate first.

Excluding them makes the result independent of order, stable when somebody adds a second supervision line, and — the part that matters when a customer asks — explainable. "Ten dollars for every thousand of actual work" is a sentence anyone accepts. "Ten dollars for every thousand of actual work plus the other overhead lines" is not.

5. The pennies

The quantity is derived rather than typed, so it is rarely round. A $200,999 base gives 200.999 thousands, and at $10 that is $2,009.99.

ClientManager keeps it exactly. No rounding up, none down. Every other line in an estimate carries its exact arithmetic, and a unit that quietly shaved the pennies would be the one line nobody could reconcile against a calculator.

6. The percentage codes

The unit list also contains %, and ImproveBuild's original list had %C, %P and %M beside it. All four were marked "future enhancement" there and never shipped.

They still calculate nothing. They are recognised as not being ordinary units, so a line carrying one is not silently extended as quantity × cost the way the dollar codes were for years — but there is no percentage arithmetic behind them. Use $C, $P or $M.

Related: Build an Estimate for the line items themselves, and Reference data you control for the unit list.