Payment Schedule

Progress billing: the milestones a contract is billed in, agreed with the client as part of the contract itself, instead of one invoice for the whole job.

Where it sits in the flow

1

The schedule comes before the signature

Open a project, go to Estimates, and press Payment Schedule on the estimate. You do this before the proposal is accepted, because the schedule is part of what the client is agreeing to.

No payment schedule, nothing to agree to. A proposal cannot be given an Accept Date until a schedule exists behind it. The order is: build the estimate → set the payment schedule → generate the proposal, which now contains the schedule → get it signed → raise the invoices.
2

This screen bills nothing

It works out the schedule and stores it. No invoice is created here, no matter what you press. Raising the invoices happens later, from the signed contract — see Raising the invoices below.

3

The contract amount tracks the estimate — until it is signed

The figure the percentages are struck against is the total of the estimates linked to the proposal. While the proposal is unsigned it follows the estimate: go back, add a line, come here again, and the contract amount and every draw have moved with it. You do not have to re-link anything or re-generate the schedule to pick up a change.

The moment an Accept Date is set, that figure is frozen. From then on it is what the client agreed to pay, and editing the estimate behind it will not move it — by design. Work agreed after signature is a change order, not a correction to the contract.

Worth knowing: this is why the WIP report and the Contract Amount column only ever count accepted proposals. They are reporting on agreed contracts, so they read the frozen figure.

Setting the terms

1

Pick the template

Payment templateWhich milestones this job is billed against — Bathroom, Basement, New Home, or one of your own. See Payment Templates for where those come from.
CreditsDesign fees and anything already paid for. Reduces what is left to bill without reducing the contract, which is why it is a separate field and not a deduction from the amount.
There is no separate deposit field. The template carries its own Deposit milestone, and that is the deposit — a second one would bill it twice.
2

Change the percentages for this contract

The template’s milestones appear underneath it with their percentages, and you can change them. Typical reason: you want more money up front on this particular job.

The milestones are fixedYou cannot add or remove lines here — the template decides which milestones a job bills at. Change the template selection and the list is rebuilt.
The percentages are yoursEdit any of them. A line moved off the template figure shows what the template said, underneath, so you can see at a glance where this contract differs.
100% or lessThe total you enter may be less than 100 but never more. Over 100 and Generate Payment Schedule is disabled — it would bill more than the contract.
Changing them here does not change the template. It applies to this contract only. To change a template for good, edit it on Payment Templates.
3

Generate Payment Schedule

This stores the schedule — the template, the credits, and the percentages as you have set them. The figures recalculate as you type, so change them freely and watch what happens; nothing is stored until you press it.

Once stored, the schedule is what the proposal prints and what the invoices are later raised from. It is not re-read from the template afterwards, so a template edited next month cannot rewrite terms a client has already signed.

The arithmetic, so none of it is a surprise

1

A worked contract

A $100,000 basement on the Basement template, left exactly as the template ships:

Explicit percentagesDeposit 20%, demolition 20%, Substantial Completion 7%, punch list 3% = 50%
Five milestones at zeroThey split the other 50% equally → 10% each, $10,000 apiece
Deposit20% → $20,000. It is a milestone like any other, not a slice taken off the top.
Last drawEvery draw is a whole dollar except the last, which absorbs the remainder so the Difference reads $0.00
A milestone left at zero is not billed at zero. This is the one rule worth reading twice. It is also why a template whose percentages add up to 50% still bills the whole contract. The screen spells out the split underneath the totals so you never have to work it out.
2

Now take more up front

Same contract, but you raise Deposit from 20% to 30%:

Explicit percentages30 + 20 + 7 + 3 = 60%
The five zero milestonesNow share 40% → 8% each, $8,000 apiece
TotalStill $100,000. The zero milestones simply take less.

That is the whole mechanism: raise one milestone and the undecided ones absorb it. You never have to rebalance the rest by hand.

It goes into the proposal

1

The contract prints the schedule

Generate the proposal from the Proposals tab as usual. The Construction Proposal now prints the schedule as a real table — each milestone, its percentage, its amount, and the total — where it used to print two blank lines to fill in by hand.

It prints the stored schedule, which is what makes the signed page and the screen agree. If you change the percentages afterwards, press Generate Payment Schedule again and regenerate the document.

Building your own proposal template? Payment Schedule is in the field picker as a repeating table under Project Proposal, with Milestone, Percentage, Amount and Order.

Raising the invoices

1

From the signed contract, on the Proposals tab

Once the proposal carries an Accept Date, a Raise Invoices button appears on its row. It raises the whole schedule at once. That is the point: the day the contract is signed, Accounts Receivable can show every payment that is coming.

You are told how many will be raised and what they total before anything is written.

Accepting the proposal locks the estimates behind it. That happens however the acceptance was recorded — electronically signed, or an Accept Date typed in by hand after a paper signature.
2

Due dates are yours to move

You set one due date when you raise them, and every invoice takes it, because at signing that is genuinely all anybody knows. It defaults to today. Edit each one afterwards on the Payment Schedule screen as the job is scheduled — a draw whose date you set by hand is marked edited, so you can tell the decided dates from the generated ones at a glance.

3

Withdraw, and raising again

Withdraw takes one unpaid draw out of the billing. Nothing is deleted — it is deactivated, so the trail stays.

Pressing Raise Invoices again rebuilds the unpaid invoices only. A milestone that has money against it keeps its original invoice and is not billed a second time.

Paid draws are never touched. A draw with money against it is accounting history and stays exactly as it is. So if you changed the percentages after part of the contract was already paid, the re-raised schedule can come out not matching the contract — the paid draws keep their old amounts while the rest are recalculated. You are told how many were left alone, so check the total afterwards.

Change orders

1

They bill themselves, separately

You do not change a signed contract. Extra work is a change order: its own estimate, its own payment schedule, its own proposal, its own acceptance. A job can collect a dozen of them as the work progresses, and each one bills independently of the contract and of the others.

So there is nothing special to learn. Create the change order as a proposal with the type Change Order, price it, set its payment schedule, get it signed, then raise its invoices exactly as you would the contract’s.

Its own percentagesA change order bills on the template’s change-order percentages where they are set, and on the ordinary contract percentage everywhere they are not. On the shipped templates one milestone differs: Start of demolition, 20% of a contract and 50% of a change order.
Its own due datesSet independently. A change order accepted in month four is not on the contract’s schedule.
Its own referenceChange order invoices are referenced CO/ and contract invoices CP/, so a statement shows at a glance which belong to the contract and which to extra work.
Raising demolition from 20% to 50% does not unbalance the schedule — the milestones left at zero share whatever is left, so they simply take less. The total still comes to the full amount of the change order.
Have a suggestion for this page, or something you'd expect it to do that it doesn't yet? Submit a ticket or suggestion — we read every one.