Progress billing: the milestones a contract is billed in, agreed with the client as part of the contract itself, instead of one invoice for the whole job.
Open a project, go to Estimates, and press Payment Schedule on the estimate. You do this before the proposal is accepted, because the schedule is part of what the client is agreeing to.
It works out the schedule and stores it. No invoice is created here, no matter what you press. Raising the invoices happens later, from the signed contract — see Raising the invoices below.
The figure the percentages are struck against is the total of the estimates linked to the proposal. While the proposal is unsigned it follows the estimate: go back, add a line, come here again, and the contract amount and every draw have moved with it. You do not have to re-link anything or re-generate the schedule to pick up a change.
The moment an Accept Date is set, that figure is frozen. From then on it is what the client agreed to pay, and editing the estimate behind it will not move it — by design. Work agreed after signature is a change order, not a correction to the contract.
| Payment template | Which milestones this job is billed against — Bathroom, Basement, New Home, or one of your own. See Payment Templates for where those come from. |
| Credits | Design fees and anything already paid for. Reduces what is left to bill without reducing the contract, which is why it is a separate field and not a deduction from the amount. |
The template’s milestones appear underneath it with their percentages, and you can change them. Typical reason: you want more money up front on this particular job.
| The milestones are fixed | You cannot add or remove lines here — the template decides which milestones a job bills at. Change the template selection and the list is rebuilt. |
| The percentages are yours | Edit any of them. A line moved off the template figure shows what the template said, underneath, so you can see at a glance where this contract differs. |
| 100% or less | The total you enter may be less than 100 but never more. Over 100 and Generate Payment Schedule is disabled — it would bill more than the contract. |
This stores the schedule — the template, the credits, and the percentages as you have set them. The figures recalculate as you type, so change them freely and watch what happens; nothing is stored until you press it.
Once stored, the schedule is what the proposal prints and what the invoices are later raised from. It is not re-read from the template afterwards, so a template edited next month cannot rewrite terms a client has already signed.
A $100,000 basement on the Basement template, left exactly as the template ships:
| Explicit percentages | Deposit 20%, demolition 20%, Substantial Completion 7%, punch list 3% = 50% |
| Five milestones at zero | They split the other 50% equally → 10% each, $10,000 apiece |
| Deposit | 20% → $20,000. It is a milestone like any other, not a slice taken off the top. |
| Last draw | Every draw is a whole dollar except the last, which absorbs the remainder so the Difference reads $0.00 |
Same contract, but you raise Deposit from 20% to 30%:
| Explicit percentages | 30 + 20 + 7 + 3 = 60% |
| The five zero milestones | Now share 40% → 8% each, $8,000 apiece |
| Total | Still $100,000. The zero milestones simply take less. |
That is the whole mechanism: raise one milestone and the undecided ones absorb it. You never have to rebalance the rest by hand.
Generate the proposal from the Proposals tab as usual. The Construction Proposal now prints the schedule as a real table — each milestone, its percentage, its amount, and the total — where it used to print two blank lines to fill in by hand.
Building your own proposal template? Payment Schedule is in the field picker as a repeating table under Project Proposal, with Milestone, Percentage, Amount and Order.
Once the proposal carries an Accept Date, a Raise Invoices button appears on its row. It raises the whole schedule at once. That is the point: the day the contract is signed, Accounts Receivable can show every payment that is coming.
You are told how many will be raised and what they total before anything is written.
You set one due date when you raise them, and every invoice takes it, because at signing that is genuinely all anybody knows. It defaults to today. Edit each one afterwards on the Payment Schedule screen as the job is scheduled — a draw whose date you set by hand is marked edited, so you can tell the decided dates from the generated ones at a glance.
Withdraw takes one unpaid draw out of the billing. Nothing is deleted — it is deactivated, so the trail stays.
Pressing Raise Invoices again rebuilds the unpaid invoices only. A milestone that has money against it keeps its original invoice and is not billed a second time.
You do not change a signed contract. Extra work is a change order: its own estimate, its own payment schedule, its own proposal, its own acceptance. A job can collect a dozen of them as the work progresses, and each one bills independently of the contract and of the others.
So there is nothing special to learn. Create the change order as a proposal with the type Change Order, price it, set its payment schedule, get it signed, then raise its invoices exactly as you would the contract’s.
| Its own percentages | A change order bills on the template’s change-order percentages where they are set, and on the ordinary contract percentage everywhere they are not. On the shipped templates one milestone differs: Start of demolition, 20% of a contract and 50% of a change order. |
| Its own due dates | Set independently. A change order accepted in month four is not on the contract’s schedule. |
| Its own reference | Change order invoices are referenced CO/ and contract invoices CP/, so a statement shows at a glance which belong to the contract and which to extra work. |