Allowances

An allowance is a budget the client chooses within — $2,500 for bathroom tile, picked later. ClientManager tracks it on the estimate line and turns the ticked lines into a schedule you can hand over with the proposal.

Setting up the list

1

Allowance Types are a reference list

Go to Admin → Reference Data → Allowance Type. Twenty-two come ready to use — Kitchen - Cabinets, Bathroom - Wall Tile, Kitchen - Appliances, Permits & Fees, Plans & Engineering and so on — and you add your own beside them.

Worth knowing: the supplied list is shared; anything you add belongs to your business alone. A remodeler who does no masonry simply never picks Brick.

Marking a line as an allowance

1

Tick it on the estimate line, then say which allowance

Open the estimate's line-item tree, edit an item, and tick Is Allowance Item. An Allowance Type dropdown appears underneath — choose the one it is.

Why it only appears when ticked: most estimate lines are not allowances, so the dropdown stays out of the way until it means something. Unticking the box clears the type again.
2

The budget is the line's own price

You do not type an allowance amount anywhere. The budget is the line's quantity times unit cost plus markup — exactly the figure the estimate already shows. One number, one place.

3

Record what the client actually chose in Actual Cost

When the client picks their tile, put what it really costs in the line's Actual Cost field. That is what turns an open allowance into a settled one, and the difference is what becomes a change order.

Important: an allowance line with no Actual Cost cannot be sent to a vendor for a quote. There is nothing to quote yet — the specification has not been chosen. Fill in Actual Cost first.

Generating the schedule

1

Project → Allowances tab → Generate from Estimate

Pick one of the project's accepted estimates and click Generate. Every ticked line with a type becomes a row on the schedule, in the same order as the estimate.

Accepted only. The schedule is part of what the client agrees to, so it is built from an estimate that has been agreed. If the dropdown is empty, no estimate on the project has an Accepted Date yet.
2

Generating again REPLACES the schedule

It does not add to it. The previous rows are superseded and the new ones take their place, so running it twice never doubles anything. The old rows are kept out of sight as a record of what the client was last given.

When you would run it again: an accepted estimate cannot be changed — you copy it and work on the copy. When that revision is accepted, generate from the new estimate and the schedule follows.
3

Read the message, especially the warning

It tells you how many allowances were scheduled and how many previous rows were replaced. If any line is ticked as an allowance but has no type chosen, it says so and tells you how many were left out.

Do not ignore that one. A line without a type is silently absent from a document the client signs — which is usually only noticed when the invoice does not match. Go back, set its type, and generate again.

Reading the schedule

1

Budget, Actual and Variance

Budget is what was quoted. Actual is what the client chose, read live from the estimate line — so recording a selection shows here straight away, with no need to regenerate. Variance is the difference, shown in red only when the client has gone over.

An allowance showing not chosen is still open. Late in a job, a column of those is a list of decisions to chase.
2

Only Notes can be edited here

Click an allowance to add a note — "client chose the upgraded tile, change order to follow". Budget and actual come from the estimate, so an edit to those here would be thrown away the next time you generate. That is why the screen does not offer it.

3

Every allowance across every project

Site-wide views → Operations → Allowances lists them all, with the project and client on each row. Useful for a sweep of what is still unchosen, or every allowance that has gone over budget.

The difference between the two places: inside a project you see and generate that project's schedule. The site-wide tab shows all of them at once and makes you pick the project before generating.

Where it fits

→

Estimate, allowances, proposal, signature

An estimate is built and accepted. Once accepted it is fixed — a change goes on a copy, which gets its own proposal. The proposal's items are generated from the approved estimate, and the allowance schedule comes from the same place, which is why the two agree. The proposal then goes to the client for signature.

→

Terms you will see

Allowance Type Is Allowance Item Actual Cost Budget Variance Accepted Estimate superseded